Do you need planning permission for panels on a garage?

Usually not in England. Class A of Part 14 of the General Permitted Development Order covers solar on a dwellinghouse and on a building situated within the curtilage of a dwellinghouse or a block of flats, so a garage in the grounds of your home, attached or detached, is within it. The limits listed for a building in the curtilage are the same as for the house itself, and the permitted development guide sets out the 2026 figures.

Three exceptions matter for garages. The order does not permit solar on a building in the curtilage of a dwellinghouse if the dwellinghouse is a listed building. In a conservation area or World Heritage Site it is not permitted on a wall, balcony or roof enclosure that fronts a highway. And the Planning Portal says that on article 2(3) land (which includes national parks, the Broads, Areas of Outstanding Natural Beauty, conservation areas and World Heritage Sites) a flat roof needs prior approval from the local planning authority first. On the wording, Class A reaches only a building within the curtilage, so a garage in a separate block elsewhere is outside it; ask the council.

In Scotland, Circular 1/2024 sets Class 6HB for a building within the curtilage of a dwelling, with a 500mm projection limit and no rights for a building in the front curtilage of the dwelling. Wales may differ from England, as the Planning Portal says.

Which garage roofs can take panels?

Garage roofMain questionWhat the sources say
Attached garage, pitched tile or slateIs the structure sound, and how long is the covering good for?Same checks as the house roof: the Planning Portal says the roof's ability to carry the load must be checked and proven.
Detached garage, pitched roofIs the building roof strong enough, and is there a supply?The Energy Saving Trust says to make sure the building roof is strong enough, and to factor in an electricity supply if there is none.
Flat roof, felt or similarIs the deck strong enough for ballast, and is the covering near the end of its life?NFRC says a roof should have enough remaining lifespan to justify a 20-to-30-year system. See the flat-roof mounting guide.
Flat roof on a light timber or metal deckCan that deck carry the added weight?BSI describes flat roofs as built either on a dense, heavy structure such as a concrete slab or on framing with a lightweight deck of metal or timber-based material.
Corrugated sheet roof on a sectional garageIs it asbestos cement?See the next section. Do not drill until it has been checked.

Whatever the type, HSE says all roofs should be treated as fragile until a competent person has confirmed they are not. The scaffolding guide covers safe access.

What if the garage roof is asbestos cement?

Crawley Borough Council says asbestos cement has been commonly used as roofing and cladding for garages and sheds, and says it is unlikely to release high levels of fibres unless subject to extreme abrasion. The danger is in disturbing it. HSE lists use of power tools (to drill, cut and so on) on most asbestos-containing materials as work that can create a significant concentration of fibres, and says not to repair or remove asbestos materials yourself without training for non-licensed asbestos work.

That matters because fixing hooks or rails to a sheet roof usually means working through it. HSE also names fibre-cement sheets as likely to be fragile, and says falls through fragile surfaces, particularly fibre-cement roofs and rooflights, account for 22% of fall-from-height fatal injuries in construction. HSE says it is often best to leave asbestos where it is if it is in good condition, and that you should tell any contractor about asbestos in your home before work starts. If asbestos is suspected, ask the installer how they would proceed. The options include testing, a different mounting plan or replacing the roof first, and HSE says you can seek advice from an environmental health officer at your local council.

How does the electricity get from the garage to the house?

The route depends on where the inverter sits. The Energy Saving Trust notes that a building without its own electricity supply adds to the system cost. Electrical work in a garage must comply with the building regulations, and the Planning Portal lists the installation of a complete new circuit among notifiable jobs, so a new supply to the garage will normally be notifiable work, best done by a registered competent person.

OptionCableWhat the IET says
Inverter in the garageAC cable to the houseA cable buried in the ground is generally required to have earthed armour or a metallic sheath, and its route must be marked by cable covers or marker tape. Depth is an engineering judgement, and IET Guidance Note 1 recommends at least 500 mm where the ground is not built to highway standard.
Inverter in the houseDC cable from the garage arraySingle insulated steel wire armoured cable is not permitted for unearthed solar DC cabling, and cannot be buried direct because the armour would need earthing. Insulated and sheathed cable in suitably impact-rated duct to N750 is the traditional answer.

So armoured cable suits the AC route but is the wrong choice for a buried DC string. The IET also treats DC-side equipment as energised even when the inverter is disconnected. For an attached garage, the IET Code of Practice recommends cables are not buried directly in walls or encased in the fabric of the building. These IET statements date from articles published between July 2024 and April 2026, so ask the installer which edition of BS 7671 applies.

Where does the inverter go?

The IET says inverters need a means of isolation on both the AC and DC sides to allow safe maintenance, so ask where each isolator will be, who can reach it, and whether the garage will stay accessible. A battery in a garage raises separate questions, covered in the battery location guide.

What should you ask before a garage roof survey?

  • What is the roof made of, and has anyone checked for asbestos cement?
  • Who will check the structure, and will the answer be in writing?
  • Is the planning position confirmed for this building, including any prior approval for a flat roof?
  • Where does the inverter go, and is the cable AC or DC?
  • Does the quote cover the electrical certificate for the new supply?

Readers who want a garage roof assessed can send an enquiry through the site's enquiry form. The flat-roof installation guide explains the checks on a flat garage roof, and glazed roofs raise different questions, covered in the conservatory roof guide.

Sources

Common questions

Can I fit panels to a garage that is not at my house?

Class A covers a building situated within the curtilage of a dwellinghouse or block of flats. A garage in a separate block elsewhere is not on that wording, so ask the council whether you need to apply.

Does the cable to the garage need building control?

The Planning Portal says electrical work in a garage must comply with the building regulations, and that installing a complete new circuit is a notifiable job. A registered competent person can self-certify. Otherwise the work needs a building control body or, in England, a registered third-party certifier.

Should the garage roof be replaced before panels go on?

If it has little life left, yes. NFRC says that if a roof does not have sufficient remaining lifespan, it should be replaced before solar panels are fitted. The removal and refitting guide explains what happens when a roof fails under an array.

Can I drill into a garage roof to test for asbestos?

No. HSE says not to repair or remove asbestos materials yourself without training, and Crawley Borough Council says to avoid sanding, scraping or drilling. HSE says you can seek advice from an environmental health officer at your local council.

Get an installation quote

By submitting you agree to our privacy policy. We never sell your details.

Get a quote
Get a quote