10kW solar system: cost, output and the G99 step (2026)

Cost, output, panel count and the grid step for a 10 kWp home system.

Quick answer

A 10 kWp solar system costs about £15,500 to £16,200 installed in Great Britain (DESNZ 2025/26 4–10 kW median and mean, Total Installed Capacity basis), before any battery. Facing south at about 35°, it makes roughly 8,900 to 10,400 kWh a year between Manchester and Cardiff, from about 21 to 23 panels of 440–475 W. On a single-phase supply it needs a G99 application and the network operator’s approval before it is connected; on a three-phase supply, up to 16 A per phase (about 11 kW) can stay on G98.

What a 10kW solar system costs

DESNZ’s 2025/26 figures put the 4–10 kW band at a median of £1,546 and a mean of £1,622 per kW on the Total Installed Capacity basis, which is the panel kWp. For 10 kWp that is about £15,500 to £16,200 installed, before any battery. Installing solar panels and batteries in a home in Great Britain is zero-rated for VAT until 31 March 2027; from 1 April 2027 the rate reverts to 5% (HMRC VAT Notice 708/6).

Paying over time: the UK government’s Warm Homes Loan Scheme opened to homeowners on 27 October 2026 through approved lenders. It covers solar panels up to £15,000 and a battery up to £15,000, the work must be done by an MCS-certified installer, and only some of its loans are interest-free. It is a loan, not a grant. We are not a lender or credit broker and do not arrange loans; the approved lenders and terms are on GOV.UK.

Median Mean
Cost per kW (4–10 kW) £1,546 £1,622
10 kWp installed £15,500 £16,200

Source: DESNZ, Solar PV cost data, 2025/26 (published 28 May 2026), Total Installed Capacity basis, all installations, rounded to the nearest £100, batteries excluded. The solar panel installation cost guide compares every size from 3 to 10 kWp.

How much electricity a 10kW system makes

Facing due south at about 35°, a 10 kWp system makes roughly 8,900 kWh a year in Manchester and 10,400 kWh in Cardiff (PVGIS v5.3 (SARAH3), 35° tilt, due south, 14% system losses, Manchester 886 to Cardiff 1,042 kWh per kWp, read October 2026). East- or west-facing roofs, shading and most of Scotland make less. The guide to how much electricity solar panels generate gives figures for other cities and roof directions.

For scale, Ofgem’s typical yearly use for a home on a single-rate meter is 1,800 kWh (low), 2,700 kWh (medium) and 4,100 kWh (high). A 10 kWp system makes well over a high-use home’s yearly total, so it suits homes with an electric car, a heat pump or both; the rest is exported, and the better fixed export rates are around 12–13p per kWh (checked October 2026).

Thinking about a 10kW system?

By submitting you agree to our privacy policy. We never sell your details.

Panels and roof space

At 440–475 W per panel, 10 kWp is about 21 to 23 panels. Whether they fit depends on the clear area of each roof face once the edges, vents and windows are allowed for, so ask each installer for a layout drawing with the quote. The solar panel sizes guide covers panel dimensions.

Grid connection

On a single-phase supply it needs a G99 application and the network operator’s approval before it is connected; on a three-phase supply, up to 16 A per phase (about 11 kW) can stay on G98. The G98 vs G99 guide explains both routes.

10kW solar system questions

How much does a 10kW solar system cost?

About £15,500 to £16,200. That is 10 kWp at the DESNZ 2025/26 4–10 kW median (£1,546 per kW) and mean (£1,622 per kW), Total Installed Capacity basis, before any battery. 0% VAT applies until 31 March 2027.

How much electricity does a 10kW solar system produce?

Roughly 8,900 to 10,400 kWh a year. That is for a south-facing roof at about 35° between Manchester and Cardiff (PVGIS v5.3). East- or west-facing roofs make less.

How many panels is a 10kW system?

About 21 to 23. That assumes panels of 440 to 475 W each.

Does a 10kW solar system need G99?

On a single-phase supply, yes. Above 16 A per phase (3.68 kW on single-phase) the installer must apply under G99 and get approval before connecting. On three-phase, up to about 11 kW can use G98.