In-roof vs on-roof solar panels
Updated 20 October 2026 · SEO Dons Editorial
What is the difference between in-roof and on-roof solar?
The difference is what happens to your roof covering. MCS 012, the MCS product standard for solar mounting kits, defines a roof-integrated installation as one where the panels or mounting system replace some or all of the roof covering. An above-roof installation is one where the panels sit above the roof covering, and the mounting system does not replace or significantly alter the covering beneath.
In practice that means on-roof panels sit on rails above tiles or slates that stay in place, while in-roof panels sit in a weatherproof tray or flashing system that takes the place of the tiles in that area. Everything else follows from that one difference.
| On-roof (above roof) | In-roof (integrated) | |
|---|---|---|
| Roof covering | Stays in place under the panels | Replaced by the panels and flashing kit across the array |
| Main water-entry risk named in MCS 012 | Penetrations through the outer roof covering | Water getting over the flashing around, between or under the panels |
| Fire performance | Shown by mounting above a non-combustible covering | Needs an in-roof kit with a fire rating suited to its position on the roof |
| Planning in England | Same 200mm limit from the roof slope applies to both | Same 200mm limit from the roof slope applies to both |
| Natural moment to fit | Any time the roof is sound | When that part of the roof covering is being replaced |
How is each type fixed to the roof?
On-roof. Roof hooks or brackets are fixed to the structure under the tiles or slates, rails are bolted to them, and the panels are clamped to the rails. MCS 012 sets a specific rule for brackets on tiles and slates: they must either be designed to transfer no load to the roof covering, or transfer an evenly distributed load that does not cause damage.
In-roof. Tiles or slates are removed across the array area, and a tray or flashing system is laid in their place, lapping under and over the surrounding courses. The panels then complete the weatherproof layer.
Either way, on a pitched roof the MCS solar standard, MIS 3002, says the system must use products tested and certified to MCS 012, and that every mounting component must be approved to work together. MCS 012 defines a complete system as all the parts needed to achieve wind uplift resistance, weathertightness and fire performance. On your quote, look for the mounting kit's make and model as well as the panels'.
How do in-roof and on-roof systems keep out rain and fire?
MCS 012 is where the two designs are tested side by side. Each certified kit must have a declared maximum design wind uplift resistance and a declared fire classification, and fitting the panels on or in the roof must not reduce the weather performance of the roof types it is approved for.
For weatherproofing on pitched roofs, the standard uses wind-driven rain tests, and it is explicit that all roof-integrated systems must be tested. It also names where water gets in. For integrated systems, the main risk is water getting over the flashing system around, between and sometimes under the panels. For above-roof systems, it is water entering through the penetrations in the outer roof covering. Products that rely only on sealant applied on site to keep water out cannot be certified under the standard at all.
Fire is the second difference. MIS 3002 says the installer must show the panels have not affected the fire performance of the roof. For on-roof panels, that can be shown by mounting them above an existing non-combustible covering; for in-roof panels, which form the main roof covering, it means using an in-roof kit with a fire rating suited to where on the roof the array sits. The standard includes a worked example, based on Approved Document B in England and Wales, linking the kit's fire classification to its distance from boundaries. On a semi-detached or terraced house, ask what classification the proposed in-roof kit has.
In-roof also changes how the roof breathes. The National Federation of Roofing Contractors publishes a guidance note, GN64, on ventilating pitched roofs and roof voids where roof-integrated panels are installed in tiled and slated roofs, so it is worth asking whether the design has been checked against it.
Do in-roof and on-roof panels need planning permission?
In England, solar panels on a house are usually permitted development, and the roof rules apply to both types. Since the rules changed on 27 August 2026, the Planning Portal sets out these limits for houses:
- On a pitched roof, panels should project no more than 200mm from the roof slope and should not sit above the highest part of the roof, excluding the chimney.
- Equipment should be sited, so far as practicable, to minimise its effect on the building's external appearance and the amenity of the area.
- Panels must not go on a building within the grounds of a listed building, or on a scheduled monument.
- In a conservation area or World Heritage Site, panels must not be fitted to a wall, balcony or roof enclosure that fronts a highway.
A 12-month transitional period runs to 27 August 2027, during which the rules as they stood before the change can still be followed. The wider changes are explained in the 2026 solar permitted development rules.
Two practical points follow. First, on-roof rails add height above the tiles, so the 200mm measurement matters most for an on-roof design. Second, an in-roof array sits closer to the roof plane, which can help with the condition about minimising the effect on appearance, but it does not override a local restriction. Councils can withdraw permitted development rights across a defined area using an article 4 direction, so in a conservation area check with the planning authority before committing to either type. The Planning Portal's guidance covers England; it notes the policy in Wales may differ.
Building regulations are a separate question. The Planning Portal says they will normally apply to roof-mounted solar, and that the roof's ability to carry the load must be checked and proven.
Is in-roof better on a new roof or an existing one?
Because an in-roof system replaces part of the roof covering, the natural time to fit it is when that covering is coming off anyway: a re-roof, an extension or a new build. Fitting it to a sound existing roof means stripping tiles that did not need replacing. An on-roof system, by definition, leaves the covering in place, which is why it suits most existing roofs.
On an existing roof, two MIS 3002 rules are worth knowing whichever type you choose:
- Roof warranties. Where the roof covering is under warranty, the warranty provider should be consulted to establish whether the installation will invalidate it. If it might, the installer must tell you in writing and get your explicit written agreement before going ahead.
- Structure. The roof structure must be checked by a suitably competent person to make sure it can take the loads of the solar system.
The in-roof solar installation guide covers the integrated method in more detail, and the pitched roof installation guide covers on-roof systems.
What about maintenance, repairs and output?
MIS 3002 says module layout should allow access for maintenance and for the emergency services, and that how often checks are needed depends partly on how easy the roof is to reach. Routine customer checks start with a visual inspection of the panels from ground level.
The bigger difference comes when something needs replacing. With an in-roof system the panel is part of the roof covering, so lifting it opens the roof. And where a mounting system is certified using a named panel model, MIS 3002 says only those panels may be used with it, which can narrow your choices for a like-for-like replacement years later. Ask which panels the in-roof kit is certified with, and whether replacements are expected to stay available.
On output, be wary of confident claims either way. The standard MCS performance estimate is calculated from the array's kWp rating, postcode region, pitch, orientation and a shading factor, so it does not include a separate allowance for the mounting type. If an installer quotes different yields for in-roof and on-roof versions of the same array, ask how the difference was worked out.
If you are weighing up both options for your home, you can request quotes through this site's form and ask for each version to be priced, and see the in-roof installation page for what the integrated route involves.
Sources
- MCS, MCS 012 The Solar Mounting Standard (Product), Issue 3.0 (10 May 2023), checked 20 October 2026.
- MCS, MIS 3002 The Solar PV Standard (Installation), Issue 6.0 (18 March 2026), checked 20 October 2026.
- MCS, Solar photovoltaic (PV) consumer guide, checked 20 October 2026.
- Planning Portal, Planning permission: solar equipment mounted on a house or a block of flats or on a building within the curtilage, checked 20 October 2026.
- Planning Portal, Solar panels: planning permission and building regulations, checked 20 October 2026.
- GOV.UK, When is permission required? (planning practice guidance), checked 20 October 2026.
- National Federation of Roofing Contractors, NFRC GN64 Ventilation of integrated PV panels, checked 20 October 2026.
Common questions
Are in-roof solar panels more likely to leak?
Both types are tested for weathertightness under MCS 012, but the standard names different weak points. For integrated systems it is water getting over the flashing around, between or under the panels; for above-roof systems it is the penetrations through the roof covering. Kits that rely only on sealant applied on site cannot be certified.
Can in-roof panels be fitted to an existing roof?
Yes, by removing the tiles or slates across the array area and fitting the flashing kit in their place. Before that, MIS 3002 says any roof warranty provider should be consulted, and the roof structure must be checked by a competent person.
Do I need planning permission for in-roof panels in a conservation area?
Not automatically. On a house, roof panels can be permitted development in a conservation area, but they must not go on a wall, balcony or roof enclosure fronting a highway, and an article 4 direction can remove the rights. The Planning Portal advises discussing with the local authority whether all the limits and conditions will be met.
Can I swap an in-roof panel for a different model later?
Possibly not. Where a mounting system is certified or listed using a named panel model, MIS 3002 says only those panels may be used with it. Ask which panels the kit is certified with before you choose it.