How long does solar panel installation take?
Updated 10 November 2026 · SEO Dons Editorial
What are the stages, and what sets the length of each?
A home solar installation moves through six stages. Only one of them happens on your roof, and it is usually the shortest. The rest are set by surveys, network operator rules, planning law and certification deadlines, each with its own published timescale.
| Stage | What happens | What sets the time |
|---|---|---|
| 1. Survey and design | Building and roof assessed, system designed, performance estimate given in writing | Survey booking, and whether the roof needs a structural engineer |
| 2. Network operator (DNO) | G98 notification after commissioning, or a G99 application before fitting | For G99, the DNO's response: government guidance says it will be in touch within 45 days for low-voltage devices |
| 3. Planning, only if needed | An application where permitted development does not cover the job | The statutory limit for most applications is 8 weeks |
| 4. Scaffold | Access put up, sometimes a few days ahead of the fitting team | Scaffold booking, plus a council licence if it stands on the pavement |
| 5. Installation and commissioning | Mounting, panels, inverter, any battery, then tests | One to two days for a typical home, according to the Energy Saving Trust, plus the weather |
| 6. Certificate and handover | MCS certificate and handover documents | No later than 10 working days after commissioning under the MCS solar standard |
How long do the survey and design take?
No rule fixes the length of this stage, but it decides most of what follows. The MCS solar installation standard, MIS 3002, says the installer must have the building assessed by a competent professional experienced in solar PV, and must have the roof structure checked by a competent person to confirm it can take the load. The technical details, including the performance estimate, must reach you in writing at or before the point the contract is awarded.
Two things can stretch it. If the roof structure is unusual, or there is any doubt at all, the standard says a qualified structural engineer must be consulted. And Planning Portal guidance says the roof's ability to carry the panels has to be checked and proven, adding that some strengthening work may be needed.
If the design was done remotely from photos or mapping, MCS requires the quote to carry a note saying the estimate used estimated values for orientation, inclination or shading, and that actual performance may be significantly lower or higher if the installed system differs. That is a good prompt to ask when someone will look at the roof in person.
Signing the contract sets a clock of its own. MCS guidance on contracts says the contract should include a timetable for supplying the goods and doing the work, including the start date, and should say who is responsible for any permissions, approvals or planning. If you sign at home or online, consumer law lets you cancel within the cancellation period without giving a reason; for a service contract that period ends 14 days after the day the contract is entered into. A trader must not begin supplying a service before it ends unless you have made an express request.
Does the network operator have to approve the system first?
That depends on the inverter size, and the full rules are in G98 vs G99 explained. For the timeline, the short version is this:
- G98, connect and notify. The system is fitted first. MCS says the DNO then has to be notified within 28 days of commissioning, so there is no wait.
- G99, apply to connect. The application goes to the DNO before the equipment is installed. Government guidance on registering energy devices, published in March 2021, says the DNO will be in touch within 45 days for low-voltage devices to approve the installation or ask for changes.
- Solar and battery together. For fully type-tested solar-plus-storage installations there is a fast-track G99 form, A1-2. It still has to be submitted before installation, but the same guidance says it reduces the connection time to 10 days or less.
The guidance also makes it the owner's responsibility to make sure the DNO has received the notification and, for an apply-to-connect device, has given authorisation before the work is carried out. Whoever fills in the forms, ask for a copy of the DNO's reply before the scaffold is booked.
What happens on installation day?
The Energy Saving Trust says an installer should take one to two days to fit solar panels on a typical home, and that scaffolding might go up a few days before the installation date. The access stage has its own rules, including a council licence when the scaffold stands on the pavement, explained in scaffolding for solar panel installation.
The on-site work then follows a fixed order:
- Mounting. Brackets are fixed into the roof structure and the rails set out. On a pitched roof, MIS 3002 requires mounting products tested and certified to MCS 012.
- Panels. Modules are lifted, clamped to the rails and wired into strings.
- Inverter and any battery. These are fixed, isolated and connected to the consumer unit. The Energy Saving Trust notes the power may need to go off briefly while the system is connected.
- Commissioning. MIS 3002 says the system must be commissioned to a documented procedure to confirm it is safe and working as designed.
Building regulations normally apply to a rooftop solar installation, according to the Planning Portal. Where the work is notifiable, MIS 3002 says the installer must make clear who will notify it and, where that is the installer's job, complete the notification before handing the system over.
When does the MCS certificate arrive?
MIS 3002 says the installation must be registered on the MCS Installation Database, and the certificate generated, no later than 10 working days after commissioning. Registration can only happen once the system is fully installed and commissioned, not before. MCS's own guidance adds one exception: for installations under its redeveloped installer scheme, the certificate creation window is 30 days.
The certificate is worth chasing if it is late. MCS says it enables customers to access eligible financial incentives and is used by energy suppliers to verify an installation's eligibility. What the handover should contain, and when each document is due, is set out in the solar handover pack checklist.
What can delay a solar installation?
When a project slips, the cause is usually one of these:
- Planning. In most cases rooftop solar needs no planning application, but permitted development does not cover a building within the grounds of a listed building, and conservation areas and World Heritage Sites carry extra rules. Where an application is needed, the statutory limit for most applications is 8 weeks.
- DNO approval. A G99 system has to wait for the DNO's authorisation before the work goes ahead, so a slow reply moves every later date.
- The roof. A structural engineer's report or strengthening work adds a step before any panels go up.
- Weather. HSE's roof work guidance says contractors should anticipate adverse weather, that rain, ice or snow can make footing as slippery as a skating rink, and that a hand-held anemometer should be used to measure wind speed at the place of work. Among the factors for deciding whether to begin, continue or suspend work, it lists the size of the material being handled, and solar panels are large, flat items to carry on a roof.
- The scaffold licence. On a pavement, the builder or scaffolding company has to get a licence from the council before the scaffold goes up.
MCS says it is the installer's duty to keep you fully informed of the installation timeline and any delays which may occur, so ask for the programme in writing and for an update whenever a date moves.
How do you get a realistic timeline for your home?
Ask every company quoting for the job to put five answers in writing: whether the system is G98 or G99 and when the DNO forms go in; whether planning applies; when the scaffold goes up and comes down; how many days the team will be on site; and when the MCS certificate will follow. Side by side, those answers say more than a headline fitting date.
The solar installation cost guide shows where these stages appear in a quote. For a standard tiled or slate roof, the pitched roof installation guide covers the fixing method step by step. When you are ready, you can request quotes through this site's form, and enquiries are passed to companies that can do the work.
Sources
- Energy Saving Trust, Rooftop solar panel installation: step-by-step guide (1 October 2026), checked 20 October 2026.
- MCS, MIS 3002 The Solar PV Standard (Installation), Issue 6.0 (18 March 2026), checked 20 October 2026.
- MCS, MCS Installations Database (MID) guidance for installers, checked 20 October 2026.
- MCS, Notifying DNOs, checked 20 October 2026.
- MCS, Solar photovoltaic (PV) consumer guide, checked 20 October 2026.
- MCS, Guidance for Contracts and Quotations, Version 1.0 (23 February 2026), checked 20 October 2026.
- GOV.UK, How to register energy devices in homes or small businesses (published 31 March 2021), checked 20 October 2026.
- GOV.UK, Determining a planning application, checked 20 October 2026.
- GOV.UK, Scaffolding rules, checked 20 October 2026.
- Planning Portal, Solar panels: planning permission and building regulations pages, checked 20 October 2026.
- HSE, Health and safety in roof work (HSG33, fifth edition), checked 20 October 2026.
- legislation.gov.uk, Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulations 29, 30 and 36, checked 20 October 2026.
Common questions
Can solar panels be fitted in a single day?
The Energy Saving Trust puts the on-site work for a typical home at one to two days, with scaffolding sometimes going up a few days earlier. Whether yours fits in one day depends on the design, the roof and the weather, so check the number of site days in the contract timetable.
Do I have to wait for the DNO before the panels go up?
Only if the system falls under G99. A G98 system is fitted first and the DNO is notified within 28 days of commissioning, while a G99 application goes in before installation and the DNO has to authorise it first.
Will the electricity be off during the installation?
Usually only briefly. The Energy Saving Trust notes the installer may need to turn the power off for a short time to connect the panels to the home's electrics. Ask the installer when that will happen so you can plan around it.
Can work start inside the 14-day cancellation period?
For a service contract signed at home or online, the trader must not begin before the cancellation period ends unless you make an express request. If you ask for an earlier start and then cancel, you may have to pay for the part of the service already supplied.
What should I do if the MCS certificate has not arrived?
Under MIS 3002 the installation should be registered and the certificate generated no later than 10 working days after commissioning, or within 30 days for installations under the redeveloped MCS installer scheme. If neither window has been met, ask the installer for the registration date, and contact MCS if it remains outstanding.