Solar handover pack: the certificates and papers you should get
Updated 10 November 2026 · SEO Dons Editorial
What should be in a solar handover pack?
Papers from the installer, the electrician, a competent person scheme or building control, the network operator and the equipment makers. The Renewable Energy Consumer Code (RECC), one of the two consumer codes MCS names, calls them the handover documents: a signed commissioning record, the relevant certificates and warranties, operating and maintenance instructions, a full description of the system and, where relevant, the MCS certificate, the compliance certificate and an invoice for the payments received. MCS tells customers of its installers to expect a handover pack on completion, including product details and the workmanship warranty, and the MCS certificate within 10 working days of completion.
| Document | Who issues it | When | More detail |
|---|---|---|---|
| MCS certificate | The MCS certified installer | Within 10 working days of completion | MCS certificate guide |
| Electrical Installation Certificate (EIC) | The electrician who did the work, on the BS 7671 form | When the electrical work is complete | Building regulations guide |
| Building Regulations certificate | The installer's competent person scheme, or the council's building control if the installer is not registered | GOV.UK says within 8 weeks of completion; regulation 20 gives the installer 30 days to pass the occupier a copy | Building regulations guide |
| Network operator evidence | The installer sends the form and the operator replies | G98: within 28 days of installation. G99: approved before installation | G98 vs G99 |
| Commissioning record and test results | The installer, signed by an authorised signatory | At commissioning | Next section |
| System description and design | The installer | The design before work starts, the description at handover | Next section |
| Operating, maintenance and emergency instructions | The installer | At handover | Below |
| Manufacturers' warranties for panels, inverter and other parts | The makers, passed on by the installer | At handover | Register any the maker asks you to |
| Workmanship warranty, insurance-backed | The installer, with an insurer behind it | At handover | Below |
| Monitoring app details and login | The installer | At handover | Taking over an account |
| Invoice for payments received | The installer | At handover | Keep with the contract |
The EIC is the electrician's certificate on the BS 7671 model form. The IET, which publishes the model forms, notes that the old completion certificate was renamed to avoid confusion with the completion certificates issued when a building is handed over. RECC's code also requires designs showing where the system will go to be given to the customer before the work starts, so keep that design with the pack.
Can the installer hold the papers back until you pay in full?
Not under RECC's code. It says handing over the documents cannot be linked to receipt of full payment and must take place promptly after the system has been commissioned. That makes the pack something to check before the final invoice is settled, in this order:
- Ask for the commissioning record and test results, signed, and the Electrical Installation Certificate, while the installer is still on site.
- Check the network operator paperwork. GOV.UK makes it the owner's responsibility to ensure the operator has received the notification and, for a system that needs approval, granted it before the work.
- Have the installer show you how to read the system's output. The Energy Saving Trust says installers run tests and should guide you through checking how much electricity the panels are generating.
- Compare the panels, inverter and mounting kit on the roof with the contract. MCS treats a product that differs from the contract as a complaint it will consider.
- Get the dates for anything still to come, such as the MCS certificate and the Building Regulations certificate, in writing.
How deposits and stage payments are protected before this point is covered in paying for solar panels.
What should the operating instructions cover?
Enough to run, stop and check the system without hunting through product manuals. Writing for electricians in May 2025, the IET said that installation work has traditionally come with electrical certification and the makers' manuals, but users of modern home installations, solar PV included, typically need brief operating and emergency procedures. It lists:
- step-by-step start-up and shutdown procedures;
- how to shut the system down in an emergency;
- safety precautions if something goes wrong;
- what the main indications, alarms and fault codes mean;
- contact details for help, repair, maintenance and warranty.
Where an app runs or monitors the system, the IET adds details such as which equipment joins the home Wi-Fi, how security updates are provided and where to download the app. MCS says its installers provide a simple maintenance guide covering common inverter signals and basic troubleshooting. The isolators those instructions refer to are explained in the wiring and isolators guide.
What if a certificate or document is missing?
- Ask the installer in writing, listing each missing item. MCS says 14 days is a reasonable maximum time to expect a response.
- Building Regulations certificate: check the installer's scheme on the Competent Persons Register on GOV.UK, and ask the council's building control, which regulation 20 requires to store copies of the notices and certificates given to it.
- MCS certificate: MCS sends a copy on the installer's behalf only if the installer is no longer MCS certified or no longer trading. The MCS certificate guide sets out the evidence it asks for.
- Network operator letter: ask the installer first; the guide for people who have bought a house with solar panels lists operators' own routes to a copy.
- Escalate: MCS takes complaints about commissioning and handover if the installer has not responded after 14 days or you are unhappy with its response. If you are not happy with the outcome, the complaint may become a dispute for alternative dispute resolution; for contracts entered into before 1 January 2025, MCS says that route is still open through the installer's consumer code, RECC or HIES.
A RECC member must keep its records for at least six years, including commissioning checks, handover packs, certificates and notifications to building control and the network operator, so ask the installer for a copy if yours goes missing.
Who will ask to see the pack later?
Keep the pack with the deeds, because three groups will want parts of it.
- Buyers' solicitors. GOV.UK says the Building Regulations certificate should be provided when the property is sold, and that a competent person scheme certificate shows up in solicitors' searches. The buying and selling checklist lists the rest.
- Export tariff suppliers, who rely on the MCS certificate and the network operator's details; see the export MPAN guide.
- Your insurer; see solar panels and home insurance.
Under RECC's code the workmanship warranty lasts at least two years and transfers to the new owner if you move, so it belongs in the pack you hand on. If you are still comparing installers, ask each for a sample handover pack alongside the quote, and send an enquiry through the quote form when you are ready.
Sources
- Renewable Energy Consumer Code, RECC (updated 5 July 2026), checked 10 November 2026.
- Solar panels (consumer guide), MCS, checked 10 November 2026.
- Consumer complaints and What to do if things go wrong, MCS, checked 10 November 2026.
- MCS certificate queries, MCS, checked 10 November 2026.
- Building regulations approval: use a competent person scheme, GOV.UK, checked 10 November 2026.
- How to register energy devices in homes or small businesses, GOV.UK (published 31 March 2021), checked 10 November 2026.
- The Building Regulations 2010, regulation 20, legislation.gov.uk, checked 10 November 2026.
- User and maintenance instructions for modern domestic electrical installations, IET Wiring Matters issue 105 (May 2025), checked 10 November 2026.
- History of model forms, IET Wiring Matters issue 82 (September 2020), checked 10 November 2026.
- Rooftop solar panel installation: step-by-step guide, Energy Saving Trust (last updated 1 October 2026), checked 10 November 2026.
Common questions
Is the handover pack the same thing as the MCS certificate?
No. The MCS certificate is one document in it. RECC's code treats the commissioning record, operating and maintenance instructions, a description of the system and the warranty details as handover documents, with the MCS certificate, compliance certificate and invoice included where relevant.
Who issues the Building Regulations certificate if the installer is not in a scheme?
Building control. GOV.UK says an installer that is not registered with a competent person scheme must submit a building notice to the local authority before the work starts, and that making sure the work complies by obtaining the certificate is the owner's responsibility.
Does the workmanship warranty pass to a buyer if I sell the house?
Under RECC's code it must last at least two years and transfer to the new owner when the customer moves home. It must also be backed by insurance, so the full term is honoured if the installer stops trading. Check the wording in your own pack, because other arrangements set their own terms.
What if the installer has stopped trading?
MCS can send a copy of the MCS certificate when the installer is no longer certified or no longer trading. Building control keeps copies of the notices and certificates it receives, and a RECC member's insurance-backed workmanship warranty is meant to cover the rest of its term.