Export MPAN: what it is and how to get one after a solar installation
Updated 23 October 2026 · SEO Dons Editorial
What is an export MPAN?
An MPAN (Meter Point Administration Number) is a unique number for a metering point. Elexon, which keeps the electricity settlement rules, defines the matching term, the Metering System Identifier, as a 2-digit number set by reference to the network operator, a 10-digit reference number and a 1-digit check number. That is 13 digits.
Metering points are either import or export. Elexon says metering systems record the flow of electricity to a site (an import) or from it (an export). UK Power Networks says a home with equipment that generates electricity, solar panels for example, will also have an export MPAN. So a house with solar can carry two numbers: the import MPAN on the electricity bill and a separate export MPAN.
The first two digits identify the network operator. The Energy Networks Association (ENA) calls them the Distributor ID, and Electricity North West gives an example: MPANs in its area begin with 16.
Who issues the export MPAN, and when?
Network operators issue MPANs, although who requests the export MPAN varies, as the table below shows. For a solar system the trigger is the grid paperwork after commissioning. GOV.UK says a connect-and-notify (G98) installation is notified within 28 days of installation, while an apply-to-connect (G99) form goes in before installation. It also makes the owner responsible for ensuring the operator has received the notification.
- Commissioning. The installer finishes and tests the system.
- Network operator step. The installer sends the G98 notification, or holds the G99 approval, and keeps the acknowledgement.
- Export MPAN. It is created, found or confirmed, depending on the operator.
- Supplier. You choose a Smart Export Guarantee (SEG) supplier and send what it asks for. The grants and funding page summarises the scheme.
Step 2 is covered operator by operator in G98 and G99 with each network operator, and the rules in G98 vs G99 explained.
How does each network operator handle export MPANs?
This is what each operator's own pages said on 22 October 2026. The ENA lookup matches a postcode to an operator.
| Network operator | What its pages say about export MPANs |
|---|---|
| UK Power Networks | An online Export MPAN finder asks for an email address and confirmation that you are the bill payer. Requests also go by email with a document checklist (below); the page says it aims to reply within 10 working days. |
| National Grid Electricity Distribution | Its online G98 form says: "We'll auto-generate your MPAN for you, but it's still a good idea to have it to hand." It gives instant acknowledgement. |
| Northern Powergrid | Lists its G98 and G99 forms, including G98 Form B for a single premises. The pages checked describe no separate export MPAN step for homes. |
| Electricity North West | For exports up to 30 kW the approval letter can go to the supplier for a SEG tariff. For exports over 30 kW you request an export MPAN. |
| SP Energy Networks | Says it can help find your MPAN, and that the supplier, not the operator, provides and connects the meter. No home export MPAN step on the pages checked. |
| SSEN | Under 30 kW the supplier arranges the export MPAN. From 30 kW to 50 kW the network planner provides it. Most suppliers want a "DNO Response" email from SSEN. |
| NIE Networks (Northern Ireland) | After the G98/NI commissioning form it arranges an import/export meter if none is fitted. Export contracts are with a supplier, and SEG tariffs are not available in Northern Ireland; see the Northern Ireland export payments guide. |
Can you find your MPAN online?
The import MPAN is already on paper: Electricity North West says you will find it on your electricity bill. The export MPAN is a separate number.
UK Power Networks is the one operator in the table with a public export lookup, and its page says the tool shows only the export MPAN details for generating equipment. Its import tool covers London, the South East and the East of England. SP Energy Networks says it can help find your MPAN if your property is in its area. The other pages checked offer no public export lookup, so keep the paper trail: the installer's notification, the operator's acknowledgement and any approval letter.
What do you need to apply, and why must it match the MCS certificate?
Of the operators checked, only UK Power Networks publishes a checklist. For an export MPAN it asks for a dated copy of the certificate from your installer, a copy of the sales invoice confirming the size and date of the installation, and photos of the control equipment, your electricity meter and the fuse holder where the cable enters the property. Treat that as a sensible starting set for any operator, not a rule for all of them.
The SEG needs the installation and installer to be MCS-certified or certified under an accredited equivalent, and MCS says a supplier might ask for the certificate when you sign up. MCS lists "Address, postcode, or Meter Point Administration Number (MPAN)" among the amendments it handles, asking for a full two-page electricity bill showing the MPAN. If an address or number differs between the certificate and the operator's records, work out which record is wrong and fix it at source before applying. The steps are in the MCS certificate guide.
What commonly goes wrong?
| Problem | What the sources say | First step |
|---|---|---|
| Meter replaced after installation, for example by a smart meter | MCS says the certificate may need amending after a meter change, with a photograph showing the make, model and serial number. | Ask the original installer. See solar meters explained. |
| Operator never received the notification | GOV.UK says the owner is responsible for ensuring it was received. | Ask the installer for the acknowledgement. |
| Supplier wants a document you do not hold | SSEN says most suppliers require a "DNO Response" email. | Ask the installer, then the operator. |
| Still on Feed-in Tariff export payments | Ofgem says you cannot receive both SEG and FIT export payments for the same electricity. | Contact your FIT licensee first. |
Sources
- Glossary: Metering System Identifier, Elexon, checked 22 October 2026.
- Metering Systems (Virtual Lead Party page), Elexon, checked 22 October 2026.
- Apply for an MPAN, UK Power Networks, checked 22 October 2026.
- Payments for exporting electricity, UK Power Networks, checked 22 October 2026.
- Find my electricity supplier and MPAN details, UK Power Networks, checked 22 October 2026.
- Who's my electricity network operator?, Energy Networks Association, checked 22 October 2026.
- Request an MPAN Number, Electricity North West, checked 22 October 2026.
- Generation G99, Electricity North West, checked 22 October 2026.
- Micro generation (G98), National Grid Electricity Distribution, checked 22 October 2026.
- Connections Application Forms, Northern Powergrid, checked 22 October 2026.
- Meters & MPANs, SP Energy Networks, checked 22 October 2026.
- Installation of up to 3.68kW per phase at one property, SSEN, checked 22 October 2026.
- G98/NI installations, NIE Networks, checked 22 October 2026.
- How to register energy devices in homes or small businesses, GOV.UK (DESNZ) (Published 31 March 2021), checked 22 October 2026.
- Smart Export Guarantee (SEG): earn money for exporting renewable electricity, GOV.UK (DESNZ and Ofgem) (Published 1 January 2020), checked 22 October 2026.
- Smart Export Guarantee (consumer guide), MCS, checked 22 October 2026.
- MCS certificate queries, MCS, checked 22 October 2026.
- Smart Export Guarantee (SEG): generators, Ofgem, checked 22 October 2026.
- Feed-in Tariffs (FIT): generators, Ofgem, checked 22 October 2026.
- Smart Export Guarantee explained, Energy Saving Trust (Last updated 20 October 2026), checked 22 October 2026.
Common questions
Can export go to a different supplier from the one I buy electricity from?
Yes. Ofgem says you can apply for a SEG tariff with any SEG licensee, and it does not need to be your current energy supplier. The export MPAN and any operator letter stay the same whichever supplier you choose.
Who is responsible if the network operator never got the G98 form?
GOV.UK puts the responsibility on the device owner to ensure the operator has received the notification, even though the installer submits it. Ask for the acknowledgement at handover and keep it with the MCS certificate.
I get Feed-in Tariff payments. Can I also claim SEG?
Ofgem says most accredited FIT installations can join the SEG if they have a smart or export meter, but not for the same electricity. You must first opt out of FIT export payments through your FIT licensee. The Energy Saving Trust adds that FIT generation payments can continue.
Do I need an export MPAN in Northern Ireland?
NIE Networks says it arranges an import/export meter after the commissioning form and that any export contract is between you and a supplier. The Energy Saving Trust says SEG tariffs are not available in Northern Ireland, so the Northern Ireland guide covers the routes that do exist.