solarpanelsandinstallation

Getting paid for solar export in Northern Ireland: suppliers' terms compared

Updated 23 October 2026 · SEO Dons Editorial

Why does the Smart Export Guarantee not apply in Northern Ireland?

Ofgem's Smart Export Guarantee (SEG) requires installations to be located in Great Britain, and the Energy Saving Trust, on a page last updated 20 October 2026, says SEG tariffs aren't available in Northern Ireland. It adds that specific suppliers may have their own export tariffs and that regulated suppliers have to provide export terms to relevant microgenerators. The Utility Regulator says micro-generators can sell exports directly to a supplier or through an agent. In practice the terms belong to the supplier, so GB rates and rules do not transfer. The Northern Ireland page covers the nation's planning, grid and sunshine data.

What happens before any export payment?

NIE Networks is the network operator that connects the system. The sequence below follows its pages, and the installer typically makes the application on the householder's behalf.

  1. The installer picks the route. G98/NI covers equipment that exports a maximum of 3.68 kW on single phase, under 11.04 kW on three-phase or under 16 amps per phase, and G99/NI applies above that.
  2. Under G98/NI the installer connects first and has 30 days from commissioning to send NIE Networks the Stage 1 form. NIE Networks says there is no application fee for a G98/NI Stage 1, and that G99/NI approval must be granted before installation begins, with application fees for every generation application except G98/NI.
  3. NIE Networks fits an import/export meter if none is installed; the meters guide and the export MPAN guide cover the meter side in more detail.
  4. The householder then approaches a supplier for a purchase contract. NIE Networks says it has no involvement in this step.

NIE Networks does not buy the electricity; suppliers do. A reader who wants installer quotes can send an enquiry through the site's quote form.

What do Northern Ireland suppliers publish about export terms?

The table lists only what each supplier's own page said when read on 22 October 2026. It does not rank the suppliers, and a missing rate means the page did not show one. Other suppliers may offer terms that are not published online, so ask before assuming.

SupplierWhat its page saysPublished export ratePage read on
Power NIRegisters generators under 50 kW and buys their exported electricity. Steps: activate a Renewable Account, set up the generating station, give an opening export reading. Payment follows an annual reading from the NIE Networks meter.11.88 p/kWh for 1 October 2026 to 30 September 202722 October 2026
Budget EnergyStates it does not offer an export tariff, that the scheme is run by Power NI and that customers should contact Power NI. Also says residential homes are eligible for microgeneration.None published22 October 2026
Click EnergyPays for the amount exported through a power purchase agreement. The agreement sets a fixed or variable rate and a contract period, and payments are by direct debit. Says an export agreement is possible even with another supplier for supply.No rate shown on the page22 October 2026

Power NI's rate is quoted as published, and its page says rates are approved by the Utility Regulator each year and published towards the end of September. As an illustration only, 1,000 kWh exported at 11.88 p/kWh comes to 11,880 p; the volume is an assumption for the arithmetic, not a typical figure.

How is exported electricity measured and paid?

The Utility Regulator's decision of 31 May 2022 removed the "deemed" method, under which micro-generators were deemed to have exported 45% on average of the electricity produced, in favour of actual meter reads, with the new settlement period starting on 1 October 2022. Power NI's pages describe the actual-reading approach: your NIE Networks meter records both imported and exported electricity, and the export payment is claimed by submitting an annual reading from that meter.

Power NI says export payments are made in late October each year for most customers, with delays possible if readings need verification or a meter has been changed, and that payments go to a bank account and do not appear on the electricity bill. It also pays for Renewable Obligation Certificates, but says that scheme closed to new generating capacity on 31 March 2017, so ROCs apply only to installations accredited before then. Click Energy says generation over 50 kW is paid monthly, which is a different rhythm from an annual reading.

What should you ask a supplier before agreeing export terms?

  • What size of system the terms cover. Power NI's pages refer to generators under 50 kW.
  • Whether the rate is fixed or variable and how long the contract runs. Click Energy says its agreement states both.
  • How and when the reading is taken, and how often payment arrives.
  • Whether export can be sold to a different supplier from the one that supplies the home. Click Energy says it can be.
  • What happens to the rate each year, since Power NI sets a new annual price from 1 October.

Sources

Common questions

Do I have to buy my electricity from Power NI to be paid for export?

Power NI's pages say a generator under 50 kW can register with it for export payments. Whether any link to electricity supply applies is worth confirming with the supplier, since Click Energy's page says an export agreement is possible even if another supplier provides the supply.

Does NIE Networks pay for the electricity I export?

No. NIE Networks says it connects the system to the grid but does not buy the electricity, and that the purchase contract is between the householder and a supplier.

How often does the export rate change?

Power NI says it offers one price a year for export, approved each year by the Utility Regulator. Its export tariff year runs from 1 October to 30 September and new rates are published towards the end of September.

Are the rates on this page current?

The only rate shown is Power NI's, for 1 October 2026 to 30 September 2027, as published on its page on 22 October 2026. Check the supplier's page before relying on it, because rates are reset each year.