G98 and G99 with each network operator: portals, forms and timescales

Updated 23 October 2026 · SEO Dons Editorial

How does each network operator take G98 and G99 for a home system?

The table records what each operator's own pages said on 22 October 2026. "Not stated" means the pages checked gave no figure. The ENA lookup matches a postcode to an operator, and the rules behind G98 and G99 are in G98 vs G99 explained.

OperatorG98 notificationG99 and fast trackStated timescales
UK Power NetworksInstaller notifies through its Smart Connect portal within 28 days of installation. Only installers can notify for customers.Smart Connect handles the ENA forms, including fast track. Maximum export under 5 kW after any limitation scheme is approved automatically; 5 kW to 50 kW goes through the same portal for review.A news item of 10 June 2024 says most domestic approvals come back in minutes. No G99 figure stated.
National Grid Electricity DistributionOnline form within 28 days of commissioning; instant acknowledgement.Fast track by online form. Standard G99 by downloaded form A1-1.Fast track: a reply within 10 working days. Standard G99: not stated.
Northern Powergrid"Apply online" request or downloadable G98 form.Forms A1.2 and A3.2 for fast-track procedures 2 and 3.Not stated.
Electricity North WestForm B by email. For an inverter, the rating counts as its continuous steady state rating.Form A1-1 with a single line diagram up to 50 kW. Do not switch on until commissioning documents are approved.Not stated.
SP Energy NetworksInform before or at commissioning; commissioning confirmation within 30 days.Forms for under 50 kW, plus a fast-track form for PV and storage each under 3.68 kW per phase.Its storage page says approval "within 10 days" if conditions are met; the page carries a 2024 copyright, so confirm.
SSENForm B by email within 28 days of commissioning. Apply first if there is more than one generator at the property.Fast track by email, then up to 3 months to install. Above 3.68 kW to 50 kW: Form A1-1.Fast track: aims to respond within 10 working days. Above 3.68 kW: up to 45 working days to a quotation.
NIE NetworksG98/NI Stage 1 commissioning form within 30 days of commissioning. Stage 2 first for several nearby installations.G99/NI Fast Track to 60 A per phase, inverter to 32 A, export limited to 16 A. Approval before installation.Connection offer within 90 days for small-scale generation once information is complete.

On the check date SSEN's pages carried a notice that its customer portal and online application services were temporarily unavailable, with contact options listed instead.

What do the stated timescales actually say?

They describe the operator's side only. Scaffold, kit and installer diaries are separate, as how long installation takes explains.

  • G98 notification: GOV.UK says within 28 days of installation. SPEN and NIE Networks give 30 days.
  • Standard G99, low voltage: GOV.UK says the operator will be in touch within 45 days.
  • Fast-track G99: GOV.UK says the A1-2 route reduces connection time to 10 days or less. ENA says the planned commissioning date must fall between 10 working days and three months after submission.

What happens when an operator sets an export limit?

An export limit caps what leaves the house; it does not stop the system running. National Grid Electricity Distribution describes limitation schemes as letting operators keep supplies within network capacity while enabling new generation, and says they would be expected to operate infrequently and for minimal duration. The settings cannot be changed by the customer without the operator's written agreement.

More paperwork comes with a limit. National Grid Electricity Distribution wants a limitation scheme form in addition to the generation forms, and a commissioning form within 28 days. Electricity North West adds G100 Form C. SP Energy Networks may witness the commissioning, with fees. SSEN says a scheme could be cheaper than network upgrades and could mean a faster connection, and that domestic generation permitted with one typically falls between 5 kW and 15 kW. UK Power Networks approves automatically when maximum export after the scheme is under 5 kW.

What do the operators have in common?

The ENA says a generator under 3.68 kW per phase falls under G98, and Electricity North West gives 11.04 kW for three-phase. The legal hook is regulation 22 of the Electricity Safety, Quality and Continuity Regulations 2002, which for sources up to 16 amperes per phase that disconnect when the network supply is lost requires the installer to ensure the distributor is advised before, or at the time of, commissioning. GOV.UK's connect-and-notify guidance and the operator pages work to 28 or 30 days, so ask for the date the notification was sent. ENA says its Connect Direct platform still accepts G98, G99 and G100 forms.

What should you ask the installer?

  • Which operator and route apply, and the date the notification or request was sent.
  • The acknowledgement or approval, kept with the MCS certificate. The export MPAN guide shows where it is needed next.
  • The inverter's rating and whether an export limit applies, in kW. Sizing is covered in what size inverter you need.

The cost guide explains what a quote should itemise. If you are planning a system, you can send an enquiry through the quote form.

Sources

Common questions

Can a network operator refuse a G98 notification?

G98 is notify-after rather than approve-first, but it is still checked. SSEN says it reviews the submission and confirms whether the connection meets G98 or needs further action, and GOV.UK says the operator will be in touch if the form is submitted incorrectly.

Does the operator charge for a home system?

UK Power Networks says there is no cost to you if the installer can finish without an electricity supply upgrade. NIE Networks says there are no application fees for G98/NI Stage 1. UK Power Networks adds that where it has to upgrade supplies, cost and timing vary.

What if the operator's online service is down?

SSEN's pages carried an outage notice on 22 October 2026 but still gave email routes for Form B and the fast-track forms. Ask the installer which route was used, and keep proof of the date it was sent.

Is Northern Ireland handled the same way?

Not exactly. NIE Networks uses G98/NI with a 30-day commissioning form and a Stage 2 route for clusters of nearby installations, and its G99/NI Fast Track needs approval before installation. The guide to solar panels in Northern Ireland sets out both routes alongside the planning and export rules.