Solar panels for flats: who must agree, who owns the roof and what can be fitted

Updated 23 October 2026 · SEO Dons Editorial

Can a flat owner fit solar panels?

Two separate sets of rules apply. Planning law decides whether a planning application is needed. The lease, or in Scotland the title deeds, decides whether you may do the work and who must agree. The Leasehold Advisory Service (LEASE) says you might need the landlord's permission before any alteration, even if you already have planning permission or building regulations approval, and the Planning Portal's solar guidance warns leaseholders too. This guide is for owner-occupiers.

Does permitted development cover flats in England?

Yes, with limits. Class A of Part 14 of the General Permitted Development Order covers microgeneration solar on a dwellinghouse or a block of flats, and on a building within the curtilage of either. The order defines a block of flats as a building which consists wholly of flats, and says a dwellinghouse does not include a building containing one or more flats. A building that mixes flats with a shop or office is therefore neither a block of flats nor a dwellinghouse on those definitions, so ask the council before assuming Class A applies.

The order has set separate limits for houses and for blocks of flats from 27 August 2026. For a block of flats the Planning Portal lists these:

  • on a pitched roof, panels should not sit above the highest part of the roof;
  • panels should project no more than 200mm from the wall surface or, where relevant, the roof slope;
  • on a flat roof, no more than 600mm above the highest part of the roof;
  • none on a building within the grounds of a listed building (the order also excludes a listed block);
  • in a conservation area or World Heritage Site, none on a wall fronting a highway.

The permitted development guide covers the 2026 changes. One rule matters on blocks with flat roofs: on article 2(3) land the developer must apply to the local planning authority for prior approval before installing solar on a flat roof. The Planning Portal says its guidance relates to England and that Welsh policy may differ.

Who owns the roof, and who must agree?

GOV.UK says most flats are leasehold. LEASE says the lease should show which parts you own and control (the demised premises) and which the landlord owns and controls (the retained premises), and the answer for the roof decides most of the questions below.

SituationWhat LEASE says
The landlord owns the roofYou cannot change parts the landlord owns without permission, and the landlord's usual duty to consent unless there is a reasonable reason to refuse does not apply where the work involves retained premises.
The lease allows alterations with consentThe request should be in writing, dated, with copies kept.
The lease bans alterationsThe landlord does not have to consider the request, so the clause would need to be varied.
Your block has a share of freeholdLEASE says leaseholders can join together to buy the building's freehold. Where that has happened, the landlord's role sits with the owners, including you, so ask how decisions are made.

If consent is needed and the work is done without it, LEASE says you could be in breach of your lease, even if a previous owner did the alteration. If the lease allows, the landlord can charge a fee for legal or other expenses of giving consent, and LEASE says such fees are administration charges, which must be payable under the lease and reasonable. The cost guide explains what drives system prices; for a flat, add consent fees and roof access to your questions.

Communal system or individual arrays?

A communal array is a project for the building, usually paid for through the service charge. LEASE describes Section 20 consultation as the process a landlord must follow when work will cost leaseholders more than a set amount through the service charge, and says major works include repairs, maintenance and improvements. It adds that you cannot prevent needed work or refuse to pay if the cost can be recovered under your lease, so whether solar is recoverable is a lease question.

Individual arrays raise a different problem: several flats, one roof. Where the roof is retained, ask the landlord how roof space would be shared between owners. The flat-roof installation guide and the flat-roof mounting guide cover what changes on a flat roof, and readers can send an enquiry through the site's enquiry form.

What changes for the network and metering when flats share a roof?

SSEN sets out extra steps for generation at more than one property, or with more than one generator at a single property, and says an application is still required even if the total is below 3.68kW. One trigger is another property in the same postcode, ignoring the last two digits, having had generation installed within the last 28 days by the same installer. Flats in one building are likely to match, so a block with several arrays can fall into this route. Other operators may differ.

SSEN also says your supplier will arrange your export MPAN where the generation is under 30 kilowatts. For a shared roof, ask how each array connects (to a flat's supply or the landlord's), where each meter sits and who owns it.

Does balcony or plug-in solar change this?

From 27 August 2026 regulations define a plug-in microgenerator as a solar source with a rated AC output of no more than 800 watts, connected by a standard plug and socket and not designed to import electricity for storage. It must comply with the Plug-in Solar Device Interim Product Specification, version 2 (16 July 2026). The planning order now counts plug-in solar as solar PV, and for a block of flats it removes the right where any part would be on a wooden wall, balcony or enclosure or a timber-clad exterior.

None of that settles the lease question. LEASE gives installing CCTV, a heat pump or an electric car charging port on the external wall as examples of lease restrictions, so a balcony fitting can need consent too. The wall-mounted solar panels guide covers other wall options.

How do Scottish tenements differ?

mygov.scot says that if your title deeds are clear on what to do, you must follow that process. The Tenement Management Scheme applies only where they say nothing, are unclear or conflict with a neighbour's. Under the scheme the roof, rafters and supporting structure are scheme property, and decisions are made by voting, one vote per property. But the scheme says maintenance does not include alteration or improvements unless part of maintenance work, and its list of matters for a scheme decision does not mention solar equipment. On this guide's reading, a rooftop array is not clearly something a majority vote under the default scheme can impose, so read the deeds and take legal advice.

On planning, the Scottish Government's Circular 1/2024 says a range of permitted development rights for microgeneration also apply to flats. Class 6HA covers solar panels on a dwelling with a 1m projection limit, and excludes listed buildings.

Sources

Common questions

Can a freeholder refuse solar on the roof?

Often, yes. LEASE says the landlord's usual duty to give consent unless there is a reasonable reason to refuse does not apply where the work involves parts of the building the landlord owns or controls. If the lease bans alterations, the landlord does not have to consider the request.

Do I need planning permission for solar on a flat?

Often not. Class A of the permitted development order covers a block of flats, within limits. A building that mixes flats with other uses, a listed block, or some conservation area walls can fall outside it, so check with the council.

LEASE says you could be in breach of the lease, even if a previous owner made the alteration. It suggests professional advice and applying for retrospective consent, working with the landlord.

Does a plug-in balcony kit need the landlord's agreement?

The regulations that cover plug-in solar deal with plug approval and product safety, not leases. If the balcony or external wall is part of the retained premises, the same LEASE guidance applies, so ask in writing before fitting anything.