Removing and refitting solar panels for roof work: what is involved

Updated 23 October 2026 · SEO Dons Editorial

Who should take the panels off and put them back?

An MCS-certified solar installer should lift and refit the array, and a roofer should do the roof. NFRC, the roofing federation, says solar installation is not just an electrical job and is a roofing decision too. The reverse also holds: the IET says electrical equipment on the DC side of a solar system should be considered energized even when the inverter is disconnected, and HSE says all work on roofs is highly dangerous, even if a job only takes a few minutes.

Using an MCS installer for the refit also keeps the paper trail tidy. To receive a Smart Export Guarantee (SEG) tariff, GOV.UK says you need to show that your installation and installer are certified through MCS or an equivalent scheme. Roof work is one of several reasons panels come down, as why people remove solar panels explains, and whether panels harm a roof in the first place is covered in do solar panels damage your roof.

What is the step-by-step sequence?

  1. Agree the roof scope first. NFRC says estimates for refurbishment work can change once the covering is removed to expose the structure underneath. If the roofer finds the whole slope is near the end of its life, decide whether to renew all of it while the panels are off.
  2. Check the paperwork before anything moves. Find the MCS certificate, the handover pack and the warranty documents, and note whether you receive Feed-in Tariff payments (see below). If the panels are old, replacing old solar panels explains whether to renew them while they are down.
  3. Book one scaffold for the whole job.
  4. Isolate, then remove. The installer isolates the inverter and treats the DC side as live. Ask for the string layout to be recorded so the array goes back as it came off.
  5. Do the roof work. NFRC says that where refurbishment covers 50% or more of a roof, either a roofer registered with its Competent Person Scheme must be employed or Local Authority Building Control contacted before work starts, to confirm the roof meets Part L thermal requirements.
  6. Refit to the mounting maker's instructions. If the covering or battens have changed, ask the installer to confirm in writing that the kit's instructions still apply.
  7. Test and recommission. The IET points to BS EN 62446-1 for grid-connected PV documentation, commissioning tests and inspection.
  8. Hand over the paperwork. Updated records, the roofer's documents and any network operator or licensee confirmations.

Why plan for one scaffold, not two?

HSE says sloping roofs require scaffolding to prevent people or materials falling from the edge, and the Planning Portal says that when working on a roof scaffolding is usually required. If the panels come off in one visit and the roofer starts in another, the scaffold goes up twice. Ask for one programme in which the installer lifts the array, the roofer finishes, and the installer refits before the scaffold comes down. The scaffolding guide covers access in more detail.

Does the network operator or the Feed-in Tariff licensee need telling?

None of the network operator, GOV.UK or MCS pages checked for this guide says whether taking down and refitting the same panels counts as a change that must be notified, so put the question to the installer before the roof work starts and ask for the answer in writing. What the pages do say: MCS says a new G98 solar installation under 16 amps per phase is notified within 28 days of commissioning, and GOV.UK says you must notify your local network operator if you make any significant change to your connection. If the works change the array size, change the inverter or add a battery, treat that as a change to report.

If you still receive Feed-in Tariff payments (Ofgem says the scheme closed to new applicants from 1 April 2019), Ofgem says you must notify your FIT licensee of modifications that change total installed capacity, including adding or removing generating equipment, and of any other modification to the accredited installation. It also says that if all of the plant up to the point of grid connection is removed, the installation is treated as decommissioned and the accreditation ends. Tell your licensee before the work starts and get confirmation that accreditation continues. GOV.UK says you cannot receive a SEG tariff while receiving Feed-in Tariff export payments, so this is not a status to lose by accident.

What happens to the MCS certificate and the warranties?

MCS describes its certificate as a record that your installation has been designed and installed to industry-recognised standards. The MCS pages checked do not say whether a removal and refit is recorded against the original certificate, so ask the installer to say in writing how the refit will be logged and what you will receive.

Warranties differ by maker. K2 Systems, a mounting maker, says in its published terms that its warranty does not apply to products that have been removed and reinstalled, except for repair purposes. Ask the makers of your mounting system, panels and inverter how they treat a refit, and ask the roofer about their cover on the new roof work. MCS says the handover pack should include workmanship warranty details, so that is the first document to find.

When is re-roofing with an in-roof system the better route?

If the covering behind the panels is coming off anyway, an in-roof kit is an alternative to refitting rails. Viridian Solar argues that with roof-integrated solar there are no tiles behind the panels, so roofing repairs can be carried out while the solar system stays in place, whereas an on-roof system must be removed before a single tile can be replaced. Marley describes new-build and full re-roof jobs as fixing the solar panels and flashing kits directly to the battens, with the surrounding covering built around them. Both are makers describing their own products.

The Energy Saving Trust says it may sometimes be recommended to renew the roof covering so that the roof stays in good condition while the panels are attached. The in-roof installation guide explains the method, the in-roof versus on-roof guide weighs the trade-offs, and the kit comparison sets the main kits side by side. Readers who want a roof and array assessed together can send an enquiry through the site's enquiry form.

What should the quote itemise?

This guide gives no removal prices. Ask for each of these as its own line.

  • Scaffold: one hire for removal, roof work and refit, and who books it.
  • Array removal: isolation, handling, storage and who is responsible for breakage.
  • Roof work: the roofer's scope, area, materials and cover, separate from the solar work, with how changes are handled once the covering is off.
  • Refit: mounting kit, any new fixings or flashings, and a statement that the maker's instructions will be followed on the new covering.
  • Electrical: isolation, reconnection, inspection, testing and recommissioning.
  • Paperwork: network operator, Feed-in Tariff licensee if relevant, MCS record and updated documents.
  • Warranty position: the effect on mounting, panel, inverter and roof warranties, in writing.

Sources

Common questions

Can I refit my own panels after the roofer has finished?

The Planning Portal says electrical installation and connections work must be carried out by a qualified electrician, and GOV.UK ties SEG eligibility to an MCS-certified installation and installer. Lifting a live array also brings the roof-work and DC risks described above. Use a certified installer.

Will taking the panels off affect my export payments?

The pages checked do not say. Ofgem says Feed-in Tariff generators must tell their licensee about modifications such as adding or removing generating equipment. For a SEG tariff, ask your supplier and the installer how a refit will be recorded.

Do I need building control for the roof work?

NFRC says that where refurbishment covers 50% or more of the roof area, either a roofer registered with its Competent Person Scheme must be employed or Local Authority Building Control contacted before work starts. The purpose is to confirm the roof meets Part L thermal requirements.

Should I replace old panels while they are down?

That depends on their age and condition, and the guide to replacing old solar panels explains the decision. Mounting-maker warranties may not carry over to reinstalled products, as K2's terms show, so ask each maker first.