Do you need planning permission for a ground-mounted array in England?

Often not, if the array stands in the garden of a house and stays inside the limits below. Class B of Part 14 of Schedule 2 to the General Permitted Development Order 2015 covers "the installation, alteration or replacement of stand-alone solar for microgeneration within the curtilage of a dwellinghouse or a block of flats". The Order defines stand-alone solar as equipment "which is not installed on a building", so a frame fixed to the ground counts. Panels on a garage or shed roof do not: they sit in Class A, which reaches "a building situated within the curtilage of a dwellinghouse" (see the garage roof guide), as do wall panels (see the wall-mounted panels guide).

Permitted development means no planning application is needed, not that no rules apply. The Planning Portal warns that "additional local rules may also affect what permissions are needed". The ground-mounted solar installation guide covers the whole job; this page covers the planning step.

What changed on 27 August 2026?

SI 2026/896, made on 29 July 2026, came into force on 27 August 2026. Its explanatory note says Class B was amended "to separate out the relevant limitations that apply to development on a dwellinghouse and development on a block of flats". For a house the differences are these.

LimitBefore 27 August 2026From 27 August 2026, house
Height4 metres; 2 metres in a conservation area nearer the highwayLowest of 4, 2 or 1 metre (table below)
BoundaryNothing within 5 metres of the boundaryAllowed, but capped at 2 metres, or 1 metre if also forward of the principal elevation
Panel size9 square metres of panels; no dimension over 3 metres9 square metres of panels; the 3 metre test is not in the house paragraph
Number of arraysOneThe one-array limit appears only in the flats paragraph
Prior approvalConservation area, nearer the highwayThat case, plus designated land within 5 metres of the boundary
Plug-in solarNo ruleNot on a wooden fence, gate, wall or other enclosure

The Order lets a developer carry out "previously permitted development" until the end of 26 August 2027, and the Planning Portal describes a 12-month transition in which either rule set can be followed. Wall panels on a house changed in the same Order: they may now project 0.4 metres, or 0.2 metres where the wall abuts a highway. Roof rules are in the permitted development post.

What are the height, area and boundary limits for a house?

Height is measured "from the surface of the ground", and the lowest limit that applies to any part of the array is the one that counts.

Where any part of the array standsHeight limit
Within 5 metres of the boundary and forward of the principal elevation1 metre
Within 5 metres of the boundary, elsewhere2 metres
In a conservation area and nearer a bounding highway than the house2 metres
Anywhere else4 metres

Three more limits apply. The panels' surface area may not exceed 9 square metres. No part may be installed within the curtilage of a listed building or on a scheduled monument. In a World Heritage Site the Planning Portal says the array should be at least 5 metres from the boundary and no nearer a bounding highway than the house.

These limits shape the frame. For example, take panels measuring 1.7 by 1.1 metres, an illustrative size and not a product. Four give 7.48 square metres and five give 9.35, so five pass the limit. Tilted at 35 degrees, a 1.7 metre panel mounted upright rises about 0.98 metres, or about 0.63 metres in landscape, before any gap under the frame. Where the cap is 1 metre, that arithmetic can decide the layout. The angle and direction guide covers tilt and output, and the frames and cable runs guide covers the build.

Where does the right not apply, or need prior approval?

  • Conservation areas. Any part nearer a highway than the house is capped at 2 metres, and the developer must first ask the council whether its prior approval is needed for the array's appearance.
  • Designated land near the boundary. The same step applies where any part is on "article 2(3) land" and within 5 metres of the boundary. The Order headlines that land as "National Parks, areas of outstanding natural beauty and conservation areas etc".
  • Listed buildings and scheduled monuments. No permitted development within a listed building's curtilage or on a scheduled monument.
  • Leasehold. A leaseholder may need permission from the landlord, freeholder or management company.

Prior approval is a wait, not a refusal. Work must not begin until the council has said in writing that approval is not required, has given it, or 56 days have passed since it received the application without a decision. The council may attach conditions.

What are the rules in Scotland, Wales and Northern Ireland?

SI 2026/896 amends the 2015 Order for England; the other nations have separate rules. The table gives what the pages in the Sources list said on 22 October 2026.

NationWhere the rule sitsMain limits for a house
ScotlandClass 3B, as set out in Planning Circular 1/2024 (28 May 2024)Not forward of a principal or side elevation wall that fronts a road; no structure over 3 metres; development on no more than half the front or rear curtilage (not counting the house or hard surfaces); not in a conservation area or a listed building's curtilage. A building warrant may be needed
WalesPart 40, Class B, 1995 Order; gov.wales summaryOne installation; 4 metres high, or 2 metres within 5 metres of the boundary; not within 5 metres of a highway; no dimension over 3 metres; 9 square metres of panels; restricted in conservation areas and World Heritage Sites; not in a listed building's curtilage
Northern IrelandPart 2, Class C, Planning (General Permitted Development) Order (Northern Ireland) 2015One installation; 14 square metres of area; 2 metres high; not nearer a bounding road than the house; not in a listed building's curtilage without consent; main purpose is energy for use in the curtilage

In Scotland the class covers garden works generally, with stand-alone panels one of the examples, so the tests are height, position and how much of the garden is built on rather than panel area.

How do you check before buying a frame?

Write down the type of land, where each part of the array will stand against the boundary and the front of the house, its highest edge and the total panel area. Then ask the council in writing. The Planning Portal says a Lawful Development Certificate suits cases where "there is a question as to whether a proposal for permitted development is legal", though it is not a replacement for planning permission, and councils may charge for pre-application advice.

An installer should state the planning route in writing before the survey ends. Electrical and building rules sit alongside planning; the building regulations guide explains them. Readers can send an enquiry through the form on this site, and the ground-mounted installation page sets out the work from survey to handover.

Sources

Common questions

Does a paddock or field count as part of the garden?

Class B applies to stand-alone solar "within the curtilage of a dwellinghouse", so land outside the curtilage is not covered by it. If you are unsure whether a paddock sits inside the curtilage of your house, ask the local planning authority in writing before buying a frame.

Can I put two separate arrays in the garden?

The paragraph for houses no longer lists a one-array limit, but the paragraph for blocks of flats still does. The Order does not say in terms that several arrays are allowed, so ask the council or apply for a Lawful Development Certificate before relying on a second one.

Do the same rules apply to a flat?

No. For a block of flats the Order keeps the older style of limits, including one installation and no dimension over 3 metres. Leaseholders in houses and flats may also need the landlord's or freeholder's consent.

Which rules apply to a frame designed before 27 August 2026?

Development permitted immediately before that date, and no longer permitted by the amended text, may still be carried out until the end of 26 August 2027. Anything the new text permits can follow the new text. Keep the planning position in writing either way.