How solar panels work on a house: panels, inverter, consumer unit and grid
Updated 23 October 2026 · SEO Dons Editorial
What are the parts of a home solar system, and which rule applies to each?
A roof system is a short chain of parts. MCS describes it as several panels connected with other parts, like an inverter and wiring, to make a full rooftop system, which is then plugged into the home's electrics. The table names each part and the rule or standard that touches it, so a quote and a handover pack can be read against it.
| Part | What it does | Rule or standard that applies |
|---|---|---|
| Panels and strings | Panels are wired in series into strings. The IET says a smaller domestic system can have just one string, and larger systems can have many. | Building regulations normally apply to a roof installation, and the roof's ability to carry the load has to be checked and proven (Planning Portal). Planning limits are in the permitted development guide. |
| DC cable | Carries direct current from the strings to the inverter. | BS 7671 Regulation 712 as described by the IET: UK systems use unearthed DC with double or reinforced insulation, and cables must not be placed directly on the surface of the roof. |
| DC isolator | Lets the DC side be disconnected for maintenance. | The IET says inverters require a means of isolation from both the AC and DC side, rated for on-load interruption. See DC isolators and PV wiring. |
| Inverter | Converts the panels' DC into the AC the home uses. | Its rating sets the grid route: Electricity North West treats the inverter's continuous rating as the rating of the installation. The network operator must be notified (GOV.UK). |
| AC isolator and connection to the consumer unit | Joins the inverter's AC output to the home's electrics. | Building regulations also cover the electrical installation, and the connection work must be done by a qualified electrician (Planning Portal). |
| Meters | Record what is exported (and, where fitted, what is generated). | For Smart Export Guarantee (SEG) payments, GOV.UK asks for a meter capable of half-hourly export readings. Details are in solar meters explained. |
| Diverter or battery (optional) | Use the surplus at home instead of exporting it. | Both are extra equipment added to the same chain; see below. |
What path does the electricity take on a sunny day?
Read as a diagram, the path runs in one direction from the roof to the grid connection:
- Panels (DC). Sunlight makes direct current in each panel, and the panels in a string add their voltage together.
- String cabling (DC). Cable runs from the roof to the inverter, wired to the rule that it is not laid on the roof surface.
- DC isolator. A point where the DC side can be switched off.
- Inverter. Turns DC into AC. The EST describes the same step: direct current passes through the inverter to become alternating current.
- AC isolator. A point where the inverter's AC side can be switched off.
- Consumer unit. The inverter's AC output joins the home's circuits, and appliances draw from it.
- Meter and grid. What the home does not use is fed back to the grid, and a meter records it.
The IET notes that a solar PV system's DC voltage depends on the module rating and on how many modules are connected in series, so a longer string means a higher voltage on the DC side.
What changes at night and in a power cut?
At night the panels make nothing, so the chain carries electricity only one way: from the grid, through the meter and consumer unit, to the appliances. This is the home as it was before the panels, and the same is true on a dull winter afternoon for whatever the panels cannot cover.
In a power cut the whole chain stops. SSEN says solar panels automatically switch off during a power cut, and Electricity North West says they stop working for safety reasons. What changes on a system with no battery is covered in solar panels without a battery.
How do a diverter and a battery fit into the chain?
Both are optional extras added to the same chain. The EST lists PV diverters and battery storage among the equipment an installer may add on installation day. A diverter uses spare electricity to power an immersion heater instead of exporting it, and how one is specified and fitted is in the diverter guide.
A battery can join the chain in two ways. SMA, an inverter manufacturer, describes one route in which a hybrid inverter runs the panels and takes the battery, and another in which a PV inverter stays in place and the battery is added "with an AC solution". The choice changes where the battery joins the chain, so it should be settled before the inverter is bought. How extras like these affect a quote is covered in the cost guide.
What paperwork does the wiring trigger?
GOV.UK lists solar PV among the devices whose owner must notify the local network operator. For a connect-and-notify (G98) system the installer submits the form within 28 days of installation, and for an apply-to-connect (G99) system it goes in before installation. The installer should be registered with a competent persons scheme, which in most circumstances lets them self-certify that the work complies with building regulations, and the owner should receive a Building Regulations Completion Certificate for notifiable work.
MCS adds its own record: the MCS certificate is due within 10 working days of completion. The deadlines, and what to do if one is missed, are covered in the MCS certificate guide, and the connection route in G98 vs G99 explained.
Sources
- Solar panels (consumer guide), MCS, checked 23 October 2026.
- Solar photovoltaic DC switch-disconnector selection and configuration (Wiring Matters, issue 109), IET (April 2026), checked 23 October 2026.
- Exploring wiring systems for unearthed DC solar PV systems, part 1 (Wiring Matters, issue 104), IET (March 2025), checked 23 October 2026.
- Building regulations: solar panels, Planning Portal, checked 23 October 2026.
- Getting your job done safely: solar panels, Planning Portal, checked 23 October 2026.
- G98, small scale connection, generation and storage, Electricity North West, checked 23 October 2026.
- How to register energy devices in homes or small businesses: guidance for device owners and installation contractors, GOV.UK (DESNZ) (Published 31 March 2021), checked 23 October 2026.
- Smart Export Guarantee (SEG): earn money for exporting the renewable electricity you have generated, GOV.UK (DESNZ and Ofgem) (Published 1 January 2020), checked 23 October 2026.
- Feed-in Tariffs (FIT): generators, Ofgem, checked 23 October 2026.
- Solar panels: costs, savings and benefits explained, Energy Saving Trust (Last updated 1 October 2026), checked 23 October 2026.
- Rooftop solar panel installation: step-by-step guide, Energy Saving Trust (Last updated 1 October 2026), checked 23 October 2026.
- Planned power cuts, SSEN, checked 23 October 2026.
- Tips to help you during a power cut, Electricity North West, checked 23 October 2026.
- Sunny Boy Smart Energy (FAQ), SMA, checked 23 October 2026.
Common questions
Does the home use the panels or the grid first?
The panels feed the home, and what the home does not use is fed back to the grid, as GOV.UK describes it. When the panels make less than the home needs, the grid covers the difference.
Why is the DC side wired differently from the rest of the house?
The IET says unearthed DC solar PV systems are the norm in the UK and use double or reinforced insulation as the protective measure, and that DC-side equipment and wiring must be Class II or equivalent. That is why DC cable is chosen and routed to its own rules and kept off the roof surface.
Do I need a generation meter?
For new export payments the requirement GOV.UK describes is a meter capable of half-hourly export readings, typically a smart meter. Ofgem says a system registered under the Feed-in Tariff must be able to measure its generation separately from other sources. Which applies to a given home depends on how the system was registered, as the meters guide explains.
Who is allowed to make the electrical connection?
The Planning Portal says electrical installation and connections work must be carried out by a qualified electrician. GOV.UK adds that installers registered with a competent persons scheme can in most circumstances self-certify compliance with building regulations.